2019 Concrete Rehabilitation Program

General Information

Tentative Start Date: Late May/Early June 2019
Tentative Completion Date: September 2019
Project Manager: Gage Miller
Contractor: TBD
Awarded Amount: TBD
Funding Source(s): Construction Fund

Contact Information

Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org

Project Manager: Gage Miller
Phone: (630) 620-5740
Email: millerg@villageoflombard.org

After Hours: Lombard Police Department
(630) 873-4400

Traffic Impact

Work on the Eastview Terrace portion of this project will have a high impact on motorists. Eastview Terrace between Charlotte and 124 Eastview Terrace will be closed. Dates are to be determined at this time. A detour will be in place during the closure. Additionally, there will be extensive panel replacement on Prairie Avenue and Ahrens Avenue. Residents on these streets will be highly impacted by the work being done. Alternate routes are encouraged for non-residents.

Communications

Notify Me: Residents and businesses within construction areas are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area.

Newsletters & Notices: Periodically, newsletters and notices will be distributed to residents to keep them apprised of current and upcoming construction related events.

FAQs

How does this benefit the Village? The proposed project will improve the drainage and driveability of the streets.

Will my road be closed? The roads in this year's project will be closed to through traffic, however, they will have one lane of traffic open at all times for residents, emergency personnel, deliveries and garbage and mail service.

If my driveway is inaccessible where do I park? Residents whose driveway is impacted by the construction will receive prior notice and parking permits allowing overnight parking on the street for the duration of their driveway closure.

Will my water or sewer service be affected? Water and sewer service will not be affected by this project.

Project Information

This project includes the reconstruction of the concrete pavement on the following streets:

  • Eastview Terrace - Charlotte to 124 Eastview Terrace

Extensive Panel Replacement on the following streets:

  • Prairie - Grace to Charlotte
  • Ahrens - Division to Washington

Concrete patching at the following locations:

  • North Avenue and Main Street, Southbound Lane
  • Finley and 22nd Street Intersection
  • 22nd Street and Westview
  • Grace - Wilson to Madison
  • Morningside - Main to Martha
  • Washington - Main to Martha
  • Hammerschmidt - Harrison to New
  • LaLonde - Pleasant to Sunset
  • Fairfield - Pleasant to Sunset
  • Joyce - Pleasant to Sunset
  •  Edgewood - Pleasant to Sunset
  •  Vista - Pleasant to Sunset

Also included in this project are minor drainage improvements, ADA sidewalk improvements at locations that need to be upgraded to current standards and select driveway apron restoration.

Construction Updates

8/6/19 - The intersection of Hammerschmidt Ave. and Harrison Rd. will be closed starting August 7th at 7 a.m. Detours will be in place until work is complete. The roadway is anticipated to be open by the end of next week.