2021 Concrete Rehabilitation Program

General Information

Tentative Start Date:  Week of August 2, 2021
Tentative Completion Date: September 30, 2021
Project Manager: Sean Kelly
Contractor: G&M Cement Construction
Awarded Contract Amount:$602,007.75
Funding Sources:  Construction Fund

Contact Information

Public Works Department
Phone: 630-620-5740
Email: publicworks@villageoflombard.org

Project Manager:  Sean Kelly
Email: kellys@villageoflombard.org
Phone: 630-620-5740

Construction Engineer:
Sarah Hodges, Robinson Engineering
Phone: 708-331-6700
Email: sarah.hodges@reltd.com

After Hours: Lombard Police Department
630-873-4400

FAQs

How does this benefit me?
The proposed project will improve the drainage and drivability of the streets.

Will my road be closed? 
Some minor delays during staging of personnel and equipment may temporarily block traffic during construction.  However, roads in this year’s project should remain open to traffic with one lane of traffic open at all times for residents, emergency personnel, deliveries, and garbage and mail service.  Through traffic will generally be discouraged.

If my driveway is inaccessible where do I park?  Residents whose driveway are impacted by the construction will receive prior notice and parking permits allowing overnight parking on the street for the duration of their driveway closure.

Will my water or sewer service be affected? 
Water and sewer service will not be affected by this project.


Communications

Notify Me: Residents and property owners are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area.

Newsletters & Notices: Periodic newsletters and notices are distributed to properties within the project area to keep residents and business owners apprised of current and upcoming construction related events. Newsletters will also be posted on this webpage.

8/3/21 -   Newsletter #1
8/4/21 - Finley Road Detour Map
9/15/21 - Newsletter #2
10/7/21 - Notice to Residents

Project Information

This Project Includes: The reconstruction of the concrete pavement on the following streets:

Elizabeth – Willow to Madison
Harding – Main to Charlotte
Grace – Harding to Taylor
Taylor – Lombard to Grace
Norbury – Madison to Taylor
Stewart – Taylor to Wilson
E. Harrison – Lalonde to dead end at the park
Vista – South of View to pond
Washington – Elizabeth to Park
22nd Street at Grace
Pleasant – Lalonde to Joyce
Berkshire – Edgewood to Vista
Finley – Wilson to Maple
Lincoln Ct
Charlotte – Harding to Madison
Alley – East of Charlotte


Miscellaneous concrete work (curb/patching) throughout the Village due to deteriorated panels and utility apron improvements.

Project Schedule:  August 2nd - September 30th, weather dependent.

Traffic Impact:   This project will have a low impact on the general motoring public, although residents on these streets having construction will be highly impacted by the work being done. Residents should exercise caution when approaching any construction traffic.  Alternate routes are encouraged for non-residents.  Highlighted streets will have brief temporary lane reductions/closures allowing for staging of personnel and equipment and concrete work.  Closures will be maintained during concrete curing (typically 3-5 days).  No detours will be posted as part of this work.

Construction Updates

10/21/21 - Finley Road between Hickory and Wilson will be detoured to Edson starting 10/22 for concrete pavement replacement.  Finley will be closed to any northbound traffic but will remain open to southbound local traffic, including to the Sunset Knoll Rec Center. The detour will be in place for approximately two weeks, pending favorable weather.  

8/3/21 - Tentative Construction Schedule for work on S. Elizabeth between Madison and Willow (weather dependent):  

    Tues-Thurs (8/3 - 8/5) - saw-cutting
    Fri & Mon (8/6 - 8/9) - removal north bound lane panels
    Tues & Wed (8/10 - 8/11) - pouring north bound lane panels
    Thurs - Sun (8/12 - 8/15) - curing northbound lane panels
    Mon & Tues (8/16 - 8/17) - removal southbound lane panels
    Wed & Thurs (8/18 - 8/19) - pouring southbound lane panels
    Fri - Sun (8/20 - 8/22) - curing southbound lane panels
    Mon (8/23) - remove traffic control 

Following the construction on Elizabeth, the contractor will pull off for a week or two, and should be back working on remaining areas in the Village starting again in early September.