2022 Concrete Rehabilitation Program
General Information
Tentative Start Date: Late June
Tentative Completion Date: End of September
Project Manager: Mike Spolar
Contractor: Schroeder & Schroeder Inc.
Awarded Contract Amount: $641,656.45
Funding Sources: Construction Fund
Contact Information
Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org
Project Manager: Mike Spolar
Phone: (630) 620-5982
Email: spolarm@villageoflombard.org
After Hours: Lombard Police Department
(630) 873-4400
Communications
Notify Me: Residents and property owners are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area.
Newsletters & Notices: Periodic newsletters and notices are distributed to properties within the project area to keep residents and business owners apprised of current and upcoming construction related events. Newsletters will also be posted on this webpage.
FAQs
How does this benefit me? The proposed project will improve drainage and drivability of the streets.
Will my road be closed? Some minor delays during staging of personnel and equipment may temporarily block traffic during construction. However, roads in this year’s project should remain open to traffic with one lane of traffic open at all times for residents, emergency personnel, deliveries and garbage and mail service. Through traffic will generally be discouraged.
If my driveway is inaccessible where do I park? Residents whose driveway are impacted by the construction will receive prior notice and parking permits allowing overnight parking on the street for the duration of their driveway closure.
Project Information
This Project Includes: The reconstruction of the concrete pavement on the following streets:
- Hammerschmidt Elementary School – South entrance at the corner of New St.
- W. Crystal Ave – between Main St. and N. Elizabeth St.
- S. Highland Ave – between E. Washington Blvd and Division St.
- E. Wilson Ave – at the corner of E. Wilson Ave. and S. Grace St.
- S. La Londe Ave – between E. Harding Rd. and E. Madison St.
- S. Grace St. – between E. Harding Rd. and E. Madison St.
- E. Harrison Rd. – between E. Taylor Rd. and E. Harrison Rd.
- S. Norbury Ave – at the corner of S Norbury Ave. and E Taylor Rd.
- E. Taylor Rd. – between S. Main St. and S. Charlotte St.
- S. Charlotte St. - between E. Taylor Rd. and E. Madison St.
- Miscellaneous concrete work (curb/patching) throughout the Village due to deteriorated panels and utility apron improvements
Project Schedule: Tentative late-June to End of September weather dependent. Actual Schedule to be determined after contract award.