Edson/Wilson Manhole Aerator

Edson and Wilson Manhole Aerator

General Information


Tentative Start Date: Week of June 18th
Tentative Completion Date: No later than August 10, 2018
Project Manager: Ray Schwab, Civil Engineer II
Contractor: Martam Construction, Inc.
Awarded Contract Amount: $111,160.00
Funding Sources: Water Sewer Capital Reserve

Contact Information


Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org

Project Manager: Ray Schwab
Phone: (630) 620-5740
Email: schwabr@villageoflombard.org

After Hours: Lombard Police Department

Phone: 630-873-4400
 

Project Information

 
Project Limits:
  The intersection of Edson and Wilson Avenues. 

Project Purpose: To alleviate sewer odors and reduce corrosion resulting from the sanitary sewer force main discharging into the manhole located within the Edson/Wilson intersection.

Project Schedule:
Bid Opening:  April 24, 2018
Project Award: May 3, 2018
Project Start:  Week of June 18th, 2018
Project Completion:  No later than August 10, 2018


Communications


Notify Me: Residents and Business Owners within construction areas are highly encouraged to sign-up for Notify Me. Notify Me will provide a more specific timeline as to traffic control will be put in place and detours will be in effect and the progress of the project. Notify Me will also alert the recipients as to exactly when the intersection will reopen. To receive timely updates regarding construction, sign up for Notify Me.

Newsletters & Notices: One notice will be mailed to residents and businesses located near the intersection. The notification will inform residents/businesses about the closure and detours. 
 
6/14   Newsletter #1
 

FAQ’s


Why is this project necessary? The elimination of sewer odor is the primary objective of the project. Current methods are only effective for a short time and still are not effective under certain weather and/or operating conditions. Like any other asset, manholes deteriorate over their service life and need to be periodically maintained. By lining the manholes, corrosion due to H2S is significantly reduced and the service life of the structure is extended.

How does this benefit the Village? The scope of the project will have three benefits. One is the reduction of sewer odors, the second is the rehabilitation of the manhole and the third is the construction of an emergency bypass in the event there are any issues related to the servicing or maintain the discharge manhole.

Will there be detours? Yes, traffic will not be allowed thru the intersection during construction. Residents along Wilson and Edson Avenues will have access to their driveways. Wilson Avenue residents who live west of the intersection should enter and leave from Finley Road. Those who live east of the intersection should access Wilson Avenue from Main or Elizabeth Streets. Residents on streets south of Wilson should use Central Avenue or Edward Street as their primary alternate east or west route. Residents on streets north of Wilson Avenue should use Ethel Avenue as their alternate east west route. Motorists who are not local residents should utilize Edward Street or Ethel Avenue as an east /west detour route.

Construction Updates

7/31/18 - The contractor placed curb and pavement on the northwest and southeast section of the intersection. Concrete work will continue through today. On Thursday, the Vortex manhole will be re-sprayed with additional cement liner. The last of the concrete pavement will be placed on Friday, with the intersection projected to reopen on 8/13, following the curing period.

7/23/18 - Schroeder & Schroeder Inc. will be doing the concrete work (curb, sidewalk & pavement) at the Edson/Wilson intersection starting July 25th. Work should be completed by the end of the month and the roadway will be re-opened after the concrete cures (pending test results). Anticipated opening of the road is August 3rd.

7/16/18 - The Village's contractor has substantially completed their work at the Edson & Wilson intersection. The traffic control will be left in place until a second contractor has completed the concrete paving of the intersection and the installation of new sidewalk at the northeast corner of the intersection. Work should resume the week of July 23rd. The intersection is on schedule to re-open in early August prior to the start of school.

7/10/18 - A sub-contractor is repairing the main manhole that will house the IPEX unit. The structure is being lined with cement and grouted as necessary. It will take one day to cure. The general contractor will be back on-site after the concrete cures to install the IPEX unit.

7/9/18 - The secondary sewer bypass is being established today. A pump is necessary to accomplish this task. There will be some noise from the pumping operation. The noise is reduced to the extent possible by a muffler and by isolating the engine to reduce vibration.

During the 4th of July Holiday, please make visitors, friend and family aware of the Edson/Wilson closure.

The contractor has removed the concrete pavement and is proceeding to install a bypass for the pressurized sanitary sewer. No work will occur on the 4th. Weather permitting, work will resume on the 5th.

Press Release: June 13

Wilson and Edson Avenue intersection to be closed to all traffic for manhole repair project

Construction to improve a sanitary sewer manhole will require the temporary complete closure of the Edson and Wilson Avenue intersection, one block east of Finley Rd., for approximately four weeks beginning June 25.

Posted detours will be in place. The completion of the project and subsequent reopening of the intersection is anticipated for the week of August 6, depending on weather.

The objective of the work is to alleviate sewer odors and reduce corrosion within the structure. The project is designed to eliminate odorous and corrosive gases by using the sewage’s own energy to oxidize odorous gases. This process will decrease unpleasant odors and will help to extend the life of the improved infrastructure.

Traffic will not be allowed thru the intersection during construction. Residents along Wilson Avenue and on Edson Avenue will maintain access to their driveways and have received mailed notification of the project details. Postal and garbage service will not be adversely affected, however some delay to the regular schedule may occur. PACE bus service will be rerouted.

Once work is completed the intersection will be kept closed for a short period to allow Village crews to patch the removed portions of the pavement. After that work is completed, the Edson/Wilson intersection will reopen. 

wilson edson manhole map