2018 Traffic Signal Modernization Program

General Information 
Start Date: August 2018
Tentative Completion Date: September 2018
Project Manager: Matthew Lew
Contractor: Meade Electric Company
Awarded Contract Amount: $141,227.94
Funding Sources: Construction Fund

Contact Information


Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org

Project Manager: Matthew Lew
Email: lewm@villageoflombard.org
Phone: (630) 620-5740

After Hours: Lombard Police Department
Phone: (630) 873-4400

Project Information


This Project Includes: The improvements include LED traffic signal heads, battery backup systems, pedestrian countdown timers, and pedestrian push buttons. 
 
Project Limits: This project will complete or upgrade eleven intersections primarily along Westmore-Meyers Road and 22nd Street.

Project Schedule: The project began Monday, 8/13 and will progress as follows:

  • Westmore-Meyers & Highridge
  • Westmore-Meyers & Wilson
  • Westmore-Meyers & Jackson
  • Westmore-Meyers & Madison
  • Westmore-Meyers & Washington
  • Westmore-Meyers & Maple
  • Westmore-Meyers & St. Charles
  • 22nd Street & Highland
  • 22nd Street & Grace
  • 22nd Street & Convention Way
  • Grace & St. Charles

Detour Map: No detours are anticipated on this project.

Traffic Impact: The project will impact traffic with temporary lane closures and associated construction work. Motorists are reminded to follow traffic signage and exercise caution within the work zone.

Communications


Notify Me: Residents and businesses within construction areas are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area. Sign up for Notify Me
 
Notices: 8/7  Press Release
 
 

FAQs


How does this benefit me?
This program will continue to improve the Village traffic signal network. This is the third year of a five year program. The program will create a more resilient traffic signal network, save energy costs to the Village through energy efficient LED technologies, provide visible pedestrian improvements, and promote a sustainable project outcome.

Will my road be closed?
No road closures are anticipated.

If my driveway is inaccessible where do I park?
Driveways are not anticipated to be inaccessible.

Will my water or sewer service be affected?
Water and sewer services are not anticipated to be affected.