Construction Update
Construction activity is continuing on the Lilac Station project. Initial excavation work is ongoing and during July sheet piling activities will start. The process for sheet pile installation consists of a vibrating hammer which is attached to the top of the metal sheet piles, which are being delivered this week, and then the piles are vibrated into the ground. This common process is required in order to allow for concrete forms and structural steel supports to be placed in the sub-grade areas. Residents and businesses should expect that this activity may increase the amount of project noise during construction hours.