General Information
Tentative Start Date: October 18, 2023
Tentative Completion Date: November 2023
Project Manager: Mike Barbier, Civil Engineer II
Contractor: John Neri Construction Co.
Awarded Contract Amount: $258,700
Funding Sources: Construction Fund
Contact Information
Project Manager: Mike Barbier, Civil Eng II/Project Mgr
(630) 620-5762 or barbierm@villageoflombard.org
After Hours: Lombard Public Works (630) 620-5740
Lombard Police Department (630) 873-4400
Communications
Periodic newsletters and hand-distributed notices will be issued as necessary.
Newsletters & Notices
Periodic newsletters and notices are distributed to properties within the project area to keep residents and business owners apprised of current and upcoming construction related events. Newsletters will also be posted on this webpage.
Project Information
Project: The scope of this project includes reconstruction of the existing junction chamber on 22nd Street, just west of Highland Avenue.
Project Limits: Westbound lanes of 22nd Street from Highland Avenue to Main Street.
FAQ’s
How does this benefit me? The proposed project will reconstruct an aging sanitary sewer manhole. This will improve the flow of the sanitary sewer and ensure the functioning of the sanitary sewer system.
Will 22nd Street be closed? Yes. 22nd Street will be closed from Highland Avenue to Main Street in order to safely and efficiently perform the necessary work. There will be a marked detour when the roadway section is closed.
What are the details on the detour? Timeframe = October 26, 2023 through November 17, 2023. (updated 10/13/23)
NB Highland Avenue to WB 22nd Street = Janata Boulevard to Main Street
SB Highland Avenue to WB 22nd Street = 17th Street to Main Street
WB 22nd Street = SB Highland Avenue to Janata Boulevard to Main Street
EB 22nd Street traffic = No change
(See Detour Map)
I live on 22nd Street will I have access to my driveway? Residents living on 22nd Street will have access to their driveways. Please use caution during work hours (7am – 4pm) as there will be construction traffic throughout these hours.
I live on 22nd Street how will this affect my garbage and refuse pick-up? There will still be garbage & recycling services provided. The Village will be in contact with Waste Management and coordinate the location of the residents’ bins on pickup days.
Will my water or sewer service be affected? Water and sewer service will not be affected by this project.