FY2024 22nd Street Shared-Use Path Improvements

General Information

Design Engineering
Start Date: November 2021
Completion Date: September 2023
Project Manager: Michael Barbier, Civil Engineer II
Engineer: Christopher B. Burke Engineering
Awarded Contract Amount: $150,499.13
Funding Sources:  MFT Engineering Fund

Construction
Start Date: April 1, 2024
Tentative Completion Date: August 2024
Project Manager: Mike Barbier, Civil Engineer II
Contractor: Triggi Construction, Inc.
Awarded Contract Amount: $1,298,698.50   
Funding Source: MFT Construction Fund & Federal Funding 
(Surface Transportation Funding)

Contact Information

Contact: Mike Barbier, Civil Engineer II / Project Manager, 
Village of Lombard Public Works
(630) 620-5762 or barbierm@villageoflombard.org
After Hours: Lombard Public Works (630) 620-5740
Lombard Police Department (630) 873-4400

Project Information

Project: This project will install a continuous 8-foot-wide shared-use path on the south side of 22nd Street from Finley Road to Meyers Road. This will not only add new path sections where only sidewalk currently exists, but it will also construct the existing areas that have an asphalt path.

Project Limits: Finley Road to Meyers Road

Timeline: Construction will start on Monday, April 1, 2024 and is anticipated to be complete in August 2024.

Frequently Asked Questions

What will be the impacts to traffic on 22nd Street? All work for the shared-use path will be limited to the south side of the 22nd Street. It is expected that there will be lane closures in the work zone for the outside lane of eastbound 22nd Street. There are no detours necessary for this project.

Will any portions of the path be open during construction? Yes. Areas of the path that are not in the work zone will be accessible to pedestrians and bicyclists.