FY2024 Concrete Roadway Restoration

General Information

Tentative Start Date: Spring 2024
Tentative Completion Date: October 2024
Project Manager: Brendan Huizinga, Civil Engineering Technician
Contractor: G & M Cement Construction
Awarded Contract Amount: $940,571.10
Funding Sources: Construction Fund

Contact Information

Project Manager: Brendan Huizinga, Civil Engineering Technician/Project Manager
(630) 620-3598 or huizingab@villageoflombard.org
Construction Engineer: John Beissel, Robinson Engineering
beisselj@villageoflombard.org
After Hours: Lombard Police Department (630) 873-4400

Communications

The “Notify Me” feature will be utilized and periodic newsletters will be issued. Hand-distributed notices will be issued as necessary.

Newsletters & Notices: Periodic newsletters and notices are distributed to properties within the project area to keep residents and business owners apprised of current and upcoming construction related events. Newsletters will also be posted on this webpage.

Newsletter #1

Project Information

Project: The preliminary scope of this project includes reconstruction of the concrete pavement on the following streets:
S Lombard Avenue – Morningside Ave to dead end
W Greenfield Ave – West Rd to Broadview Ave
West Rd – Greenfield Ave to View St
S Stewart Ave – Madison St to Morningside Ave
E Maple Ave – S Lewis Ave to S Edgewood Ave
E Pleasant Ln – N Edgewood Ave to Vista Ave
Crystal Ave – Main St to Dupage Ave
E Sunset Ave and Westwood Ave intersection
Lombard Fire Station at 50 E St. Charles Rd
Harrison - Lombard to Grace
Harrison - Fairfield to Madison Meadows Park

Miscellaneous concrete work (curb/patching) throughout the Village due to deteriorated panels and utility apron improvements.

FAQ’s

How does this benefit me?  The proposed project will improve the drainage and drivability of the streets.

Will my road be closed?  At the other locations, some minor delays during the staging of personnel and equipment may temporarily block traffic during construction. However, these roads should remain open to traffic with one lane of traffic open at all times for residents, emergency personnel, deliveries, and garbage and mail service. Through traffic will generally be discouraged.  

 If my driveway is inaccessible where do I park?  Residents whose driveway are impacted by the construction will receive prior notice and parking permits allowing overnight parking on the street for the duration of their driveway closure

 Will my water or sewer service be affected?  Water and sewer service will not be affected by this project.