Charles Lane Basin Improvements
General Information
Tentative Start Date: Summer 2026
Tentative Completion Date: 2026/2027
Project Manager: Ray Schwab, Civil Engineer II
Design Engineer: Engineering Resource Associates (ERA)
Current Contract Amount: $183,712.00
Contractor: TBD
Awarded Contract Amount: TBD
Funding Sources: Construction Fund
Contact Information
Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org
Project Manager: Ray Schwab, Civil Engineer II
Email: schwabr@villageoflombard.org
Phone: (630) 620-5740
Construction Engineer: TBD
After Hours: Lombard Police Department
(630) 873-4400
Communications
Public Meeting: No public meeting will be held. Local residents will be informed via newsletter as what to expect during construction.
Notify Me: Residents and property owners are encouraged to sign up for Notify Me to receive timely updates regarding construction activities and potential delays regarding entering and leaving their properties.
Newsletters & Notices: Periodic newsletters and notices are distributed to properties surrounding the project area to keep residents apprised of current and upcoming construction related events. Newsletters will also be posted on this webpage.
Project Information
This Project Includes: Improvements to the Charles Lane Basin which is a 7.75-acre wetland stormwater detention that serves approximately 470 acres containing roughly 1,600 homes. The objective of the project is to improve overall stormwater operations, facility maintenance, and neighborhood aesthetics. The proposed design shall integrate stormwater quality, streambank protection, and improvements to the pump station located at the southwest portion of the property. The design will also utilize the natural drainage system to minimize maintenance.
The scope of work includes the removal of the center manhole and the perimeter fence. The scope also includes the installation of flared end sections, outlet grates, and a sidewalk along the west side of Finley Road.
Project Schedule: TBD. Dependent upon a stormwater permit to be issued by DuPage County
Project Limits: Charles Lane Detention Pond (Area west of Finley Road, north of Charles Lane, east of Route 53 and South of Hickory
Traffic Impact: Potential lane reduction on Finley Road between Charles Lane and West Hickory Street. Some delays entering and leaving Charles Lane.
FAQs
How does this benefit me?
Less flooding and better drainage
Improvements to the basin and pump station will help the system work more efficiently during heavy rain. That means a lower risk of water in your yard or street, and more reliable performance when storms hit.
Cleaner water and a healthier environment
The upgraded basin will better filter out pollutants, sediment, and debris before water flows downstream. This improves local water quality and supports healthier plants and wildlife in the area.
Protection of property and infrastructure
Stabilizing the streambanks will reduce erosion, helping protect nearby properties, utilities, and public infrastructure from long-term damage.
A more attractive neighborhood
The project will enhance the look and accessibility of the area by removing the existing fence and adding a sidewalk along the west side of Finley Road. This creates a more open, visually appealing space that can improve neighborhood character and may positively influence property values.
Will my road be closed? Finley Road and Charles Lane will be subject to lane reductions or short delays for material deliveries or construction activities by the Finley Road and Charles Lane Pumping Stations and at the Finley Road and Charles Lane intersection.
If my driveway is inaccessible, where do I park? Driveways should be accessible, subject to some delays related to pump station renovations and construction traffic.
Will my water or sewer service be affected? No water or sewer service disruptions are anticipated.