St Charles Road Crosswalk Improvements Begin in April

Community Updates Posted on March 20, 2025 | Last Updated on May 02, 2025

The Village of Lombard will begin infrastructure improvements on St. Charles Road starting the week of April 14, 2025 (weather permitting). This project includes the installation of concrete crosswalks from Elizabeth Street to Craig Place and is expected to continue through late May.

Residents and businesses should expect temporary lane closures, street closures and detours throughout the construction period. Signage will be posted at least one week in advance to help guide traffic and pedestrians safely.

Tentative Construction Schedule (Updated 5/2)

    Completed:  Eastbound (phase 1) traffic only from Elizabeth St. to Garfield St.

    Current – May 3:  Westbound traffic only from Elizabeth St. to Garfield St.

    May 5 – May 9:  Eastbound (phase 2) traffic only from Elizabeth St. to Garfield St.

    May 12 – May 23:  Road closures on Craig Pl., Garfield St., Charlotte St., Main St., Park Ave., S. Lincoln Ave. and N. Lincoln Ave.

    May 26 – June 6: Road closures on Park Ave., Main St. and Martha St.

Please allow yourself extra travel time and follow all detour signs to ensure the safety of work crews, drivers and pedestrians.

Thank you for your patience as the Village makes these improvements. For more information and project details, visit https://www.villageoflombard.org/560/FY2024-St-Charles-Road-Resurfacing-Proje